GlossaryOverall equipment effectiveness
Overall equipment effectiveness
Overall equipment effectiveness, or OEE, is a measure of how well a machine or line uses its planned production time. It multiplies three rates: availability, performance and quality. A score of 100 percent means the equipment ran the whole planned time, at its ideal speed, making only good units.
How it works
The three parts each capture a kind of loss.
- Availability is run time divided by planned production time. It counts losses from breakdowns, changeovers and other stops.
- Performance is actual output divided by what the equipment makes at its ideal cycle time during the run time. It counts slow running and short stops.
- Quality is good units divided by total units. It counts scrap and rework.
OEE is the product of the three. For example, a line that runs 80 percent of planned time, at 90 percent of ideal speed, with 95 percent good units, has an OEE of about 68 percent. The Lean Enterprise Institute describes OEE as a total productive maintenance measure, and ISO 22400-2 defines it among standard manufacturing key performance indicators.
OEE vs utilization
Utilization usually means the share of time a machine is running. OEE goes further. A machine that runs all shift but slowly, or makes many bad units, can show high utilization and low OEE. OEE exposes speed and quality losses that utilization hides. Utilization also often measures against all calendar time, while OEE measures against planned production time, so the two numbers answer different questions: one is about how much the equipment is scheduled, the other about how well it performs when it is.
Why it matters
OEE turns many small losses into one number, and its three parts show where to look. On an SMT line, low availability points to changeovers and stops, low performance points to feeder faults, pick errors and slow programs, and low quality points to defects. Tracking each part over time shows whether changes work.
In a high-mix, low-volume shop, availability is usually the weakest part, because lines change jobs many times a day. Shorter changeovers raise OEE more than faster placement does. Performance also suffers on small jobs, since the first boards of each job run slower while programs are checked and adjusted.
OEE also connects equipment to cost. Every point of OEE lost is planned time paid for but not used to make good units. When a shop is deciding whether to buy another machine, a higher OEE on the existing line is often the cheaper way to get the same output.
How to get it right
- Define terms carefully. Decide what counts as planned time, ideal cycle time and a good unit, and keep those definitions fixed so scores compare over time.
- Collect data automatically. Manual logs miss short stops and slow cycles. Machine data from the MES or a factory protocol is more complete.
- Look at the parts, not only the total. A stable OEE can hide a rise in one loss and a fall in another.
- Compare a line with itself. OEE values vary by product mix and definitions, so comparing one line over time is more useful than comparing it with another factory.
- Account for mix. In high-mix work, changeover losses dominate. Shops often track changeover time per job alongside OEE, so the effect of each setup improvement is visible.
OEE in robotics and drone hardware
Lines that build robotics and drone boards in small lots spend much of their time changing over. They also spend more time on first articles, program checks and test, because each job is new or newly revised. OEE, broken down by loss type, shows how much time goes to building and how much goes to setup, programming and test. That tells a team whether to invest in faster changeover, more test stations or better first-pass yield.